Whereas the Council undertook a Condition Assessment of existing recreation facility inventory, a Community Recreation Facility Needs Assessment and updated the 2009 Recreation Master Plan in 2019;and
Whereas Council has spent considerable time, effort and resources examining various scenarios to consider a facility that the municipality can financially afford and be able to meet overall objectives for all recreation users in the community; and
Whereas we have not heard back from the Ontario Government regarding our application submitted under the Investing in Canada Infrastructure Program – Community Culture and Recreation Stream (ICIP-CCR) submitted in accordance with program requirements in November 2019 as per Council Resolutions 480-2019 – 493-2019 inclusive;
Now therefore be it resolved that Council move forward with renovating the existing South Huron Recreation Centre with a focus on the following components:
That if we have not heard back from the Provincial Government by February 28, 2021 regarding the status of our application under the Investing in Canada Infrastructure Program – Community Culture and Recreation Stream (ICIP-CCR) that Resolutions 480-2019 – 493-2019 be repealed; and
The following renovation take place at the South Huron Recreation Centre beginning as soon as possible in 2021:
- Replacing 6 new dressing rooms (1000 sq. ft each);
- Officials Room and Storage Room (1000 sq. ft. each);
- Replace Dasher Board system and if possible convert the arena floor to 200feet x 85 feet;
- AODA improvements to the existing washroom and provision of a LUL Lift
- Arena Floor, Piping be replaced;
- Epoxy on Roof – 10 year life extension and incorporated as part of regular maintenance;
- LED Lighting Upgrades
- Industrial Kitchen renovations
- Addition of a Single Gymnasium with walking track (Design Build) which would include
- moveable divider wall
- 2 dressing rooms
- Bleachers Pull-out
- Raised Walking Track; and
That the CAO be empowered prepare a building program report with costings, timeline; resource needs and construction schedule within 30 days of Council approval of this motion; and
That prior to Council authorization, this Notice of Motion be forwarded to the February 16, 2021 Council meeting with a recommendation to be placed on the February 22, 2021 Committee of the Whole for discussion